A motorcycle workshop in Arusha has 4 staff members. Their daily attendance records show:
- Mtui: Started at 8:00 AM, ended at 5:00 PM, 1 hour lunch
- Juma: Started at 8:00 AM, ended at 5:00 PM, 1 hour lunch
- Rashidi: Started at 8:30 AM, ended at 5:00 PM, 1 hour lunch
- Faraji: Started at 8:00 AM, ended at 4:00 PM, 30 minutes tea break
Calculate total man hours for the day:
Mtui:
8:00 to 17:00=9 hours−1 hour break=8 hours
Juma:
8:00 to 17:00=9 hours−1 hour break=8 hours
Rashidi:
8:30 to 17:00=8.5 hours−1 hour break=7.5 hours
Faraji:
8:00 to 16:00=8 hours−0.5 hour break=7.5 hours
Total man hours:
8+8+7.5+7.5=31 man hours
This information helps the workshop manager plan how many jobs can be handled in a day and calculate labour costs accurately.