Topics in this sectionCompound Proportions, Mixtures and Rates of Work2 topics
- Proportionality Problems
- Work Problems
Work Problems: When Workers and Machines Team Up
In everyday life, we often see several people or machines working together to finish a job. A group of farmers may cultivate a field using different tractors. Several workers may fill a water tank for a school. A team of builders may construct a classroom. In each case, we can use mathematics to figure out how long the whole job takes when everyone works together.
The key idea is that every worker or machine has its own work rate — the fraction of the whole job it can finish in one unit of time. When workers combine their efforts, we add their rates together to find the combined work rate.
If a worker can finish a whole job alone in t units of time, then their work rate is:
Rate=t1 jobs per unit time
For example, if a tractor can cultivate a field alone in 6 hours, its rate is 61 of the field per hour.
When two workers work together, their combined rate is the sum of their individual rates:
Combined rate=t11+t21
To find the time T they need working together, we use:
T=Combined rate1=t11+t211
Two tractors are used to cultivate a large piece of land near Juba. Tractor A can finish the work alone in 10 hours. Tractor B can finish alone in 15 hours. How many hours will it take if both tractors work together?
Solution
First, find each tractor's work rate:
- Tractor A rate: 101 of the land per hour
- Tractor B rate: 151 of the land per hour
Next, add the rates together:
Combined rate=101+151=303+302=305=61
The combined rate is 61 of the land per hour. This means they finish 61 of the job each hour.
Now find the time by taking the reciprocal:
T=611=6 hours
Answer: Both tractors working together will finish the land in 6 hours.
Notice that the combined time (6 hours) is less than either tractor working alone (10 hours or 15 hours). When workers team up, the job gets done faster.
The same method works for any number of workers. Simply add all their individual rates together.
If three workers can finish a job in 5 hours, 8 hours, and 20 hours respectively working alone, their rates are 51, 81, and 201 jobs per hour. The combined rate is:
51+81+201=408+405+402=4015=83
So working together, they finish 83 of the job per hour, and the total time is:
T=831=38=232 hours
Consider a water tank at a school in Wau. One tap can fill the tank in 12 minutes. A second tap can fill it in 18 minutes. The drain pipe is open and lets water out at a rate that would empty a full tank in 36 minutes. If all three are open at the same time, how long will it take to fill the tank?
Solution
This problem introduces a drain, which works against the taps. We treat the drain as a negative rate.
- Tap 1 rate: 121 of the tank per minute
- Tap 2 rate: 181 of the tank per minute
- Drain rate: −361 of the tank per minute (negative because it empties)
Add all three rates:
Combined rate=121+181−361
Find a common denominator (36):
363+362−361=364=91
The net rate is 91 of the tank per minute. So the tank will be filled in:
T=911=9 minutes
Answer: The tank fills in 9 minutes when both taps and the drain are open.
- Individual rate — the fraction of a job one worker completes in one unit of time
- Combined work — when two or more workers or machines work together on the same job
- Simultaneous work — all workers doing their job at the same time
- Find each worker's individual rate by taking the reciprocal of their solo time: time1
- Add all the rates together (remember to subtract rates for any work going in reverse, like a drain)
- Take the reciprocal of the combined rate to find the total time
- Check that your answer makes sense — it should be less than the fastest worker's solo time
In South Sudan, work problems appear in many practical situations. For example, at a boma market in Malakal, two water carriers may fill a large storage container — one takes 20 minutes alone, the other takes 30 minutes. Using the combined work formula, they can figure out that working together they will fill the container in 12 minutes, allowing them to serve more customers faster. Similarly, a construction crew with different workers building a classroom can calculate total completion time using these same steps.
Question
What is the work rate of a water carrier who can fill a large container alone in 20 minutes?
Sign in to submit your answer and have it count toward your mastery.