Mada za sehemu hiiEstimating materials and labour costMada 3
- Maintaining records of workshop materials
- Maintaining man hours/day workshop staff
- Performing job cost calculations
Maintaining Records of Workshop Materials
Workshop materials such as resistors, capacitors, wires, soldering iron tips, and printed circuit boards (PCBs) have value. When you do not record what comes in and what goes out, you may run out of important items during a repair job, waste money buying things you already have, or be unable to account for missing tools. Good record-keeping helps you know exactly what you have, what you have used, and when you need to order more.
Stock Level
The quantity of each item you have in the workshop at any time. You calculate stock level by taking the opening stock, adding any receipts, and subtracting any issues (items used or given out).
Current Stock=Opening Stock+Receipts−Issues
Reorder Point
The minimum quantity of an item that signals you to order more. When stock falls to this level, you must prepare a new purchase order so you do not run out before new items arrive.
Usage Record
A written note of every item taken from the workshop store for a job. Each record shows the date, item name, quantity taken, and the job or student who took it.
| Document | Purpose |
|---|---|
| Goods Received Note (GRN) | Filled when new materials arrive. Shows what was ordered versus what was actually received. |
| Local Purchase Order (LPO) | A formal request to buy new materials from a supplier. |
| Material Requisition Voucher (MRV) | Filled when someone takes materials from the store for a job. |
| Job Card | Records all materials and labour used on a specific repair job. |
| Price List | Shows the cost of each item, used for estimating job costs. |
| Stock Log Book | A running record of all receipts and issues for every item. |
- Make a list of all items you will store. Include names, unit of measurement (pieces, metres, rolls), and codes if any.
- Assign an opening stock count for each item at the start of the term or month.
- Create simple record sheets — either a physical logbook or a spreadsheet with columns for: Date, Item, Receipts, Issues, Balance.
- Every time materials come in, fill in the GRN and update the stock balance.
- Every time materials are taken, fill in the MRV or Job Card and subtract from the balance.
- Check the balance regularly — at least once a week. When the balance reaches the reorder point, prepare an LPO.
- File all documents (GRN, LPO, MRV, Job Cards) in a folder or bind them together so they can be reviewed later.
Mwanza Technical Workshop started the month of March with 50 pieces of 10kΩ resistors. During the month, the following transactions occurred:
- March 5: Received 100 pieces from Tunu Electronics (GRN No. 001)
- March 12: Issued 30 pieces for Job No. 15 (repair of a radio)
- March 20: Issued 20 pieces for Job No. 16 (repair of a TV amplifier)
- March 25: Received 80 pieces from Tunu Electronics (GRN No. 002)
Calculate the closing stock and identify if a reorder is needed if the reorder point is 40 pieces.
Step 1: Opening stock = 50
Step 2: Add receipts
- March 5: +100
- March 25: +80 Total received = 180
Step 3: Subtract issues
- March 12: -30
- March 20: -20 Total issued = 50
Step 4: Calculate closing stock Closing Stock=50+180−50=180 pieces
Step 5: Compare with reorder point Current stock (180) is greater than reorder point (40). No reorder is needed yet.
If the closing stock had been below 40 pieces, the workshop technician should prepare a Local Purchase Order to buy more 10kΩ resistors.
- Write clearly and use ink that does not erase easily.
- Never skip a line — record every transaction, no matter how small.
- Double-check your math before filing the documents.
- Keep digital backups if you use a computer spreadsheet.
- Store documents in a dry, safe place away from oil and dust.
When you complete your studies and work as an electronics repair technician in Tanzania, you will need to manage your own small workshop or work in a repair shop. If a customer brings a damaged television for repair and you use three electrolytic capacitors, two metres of connecting wire, and one hour of your labour, you must record these on a job card. This record lets you charge the customer the correct amount (for example, TSh 5,000 for capacitors, TSh 2,000 for wire, plus labour), ensures you replace the used capacitors from your stock, and helps you know when to buy more capacitors so you never miss a repair job.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
- Select tools and equipment
- Read inspection report
- Store tools, equipment and materials
Tathmini ya matokeo
Cost estimates of materials and labour prepared as per task requirements.
Tathmini ya maarifa
Knowledge evidence:
Detailed knowledge of:
Method used: The student should explain how to:
- Maintain record of workshop materials
Principles: The student should explain the principles of maintaining a record of workshop materials
Theories: The student should explain:
- maintaining a record of workshop materials
Circumstantial knowledge:
Detailed knowledge about:
- Safe handling of materials and documents
- Waste disposal.
Swali
What is the main reason for keeping records of workshop materials?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado