Mada za sehemu hiiPerforming cost and estimatingMada 4
- Analysing labour costs
- Analysing material costs
- Preparing a budget
- Preparing prices
Labour cost is the total amount of money a business spends on workers who make its products. In leather goods and footwear production, analysing labour costs helps a producer know how much of the selling price goes to paying workers, so they can price products correctly and make a profit.
Labour cost is not just the basic wage. It includes several parts:
- Basic wage – the money paid for normal working hours
- Overtime pay – extra payment for hours worked beyond normal working time, usually at a higher rate
- Allowances – extra money given for things like transport, housing, or skill
- Employer contributions – money the employer pays for things like NSSF (National Social Security Fund)
- Bonuses and incentives – extra rewards for good performance or meeting targets
- Direct labour is the pay of workers who work on the product itself: cutters, stitchers, assemblers and finishers. It is a direct cost, because it can be traced to each pair of shoes or each bag.
- Indirect labour is the pay of people who support production but do not make the product, such as a supervisor, storekeeper, cleaner or guard. It is an indirect cost and is counted with the overheads, together with rent, electricity and machine repairs.
On a cost sheet, the costs of one product or one order are listed in this order: direct materials (from the materials specification sheet and the suppliers' prices), direct labour, then a share of the overheads. Adding them gives the total cost.
To find the total labour cost for a worker or a group of workers, use this formula:
Total Labour Cost=Basic Wage+Overtime+Allowances+Employer Contributions+Bonuses
For a leather goods producer, it is important to know how much labour cost is contained in each item made. This is called labour cost per unit:
Labour Cost Per Unit=Number of Units ProducedTotal Labour Cost
This helps a producer set the right selling price for each shoe, bag, or belt.
To estimate the labour cost of a new product, time a worker making it and multiply:
Labour cost of one product = time taken (hours) × rate per hour
For example, a belt that takes 1.5 hours at TZS 2,000 per hour has a labour cost of 1.5 × 2,000 = TZS 3,000.
Producers also measure how efficiently labour is used:
Labour Productivity=Total Hours WorkedNumber of Units Produced
Higher productivity means each hour of work produces more items, which can reduce the labour cost per unit.
Mariam makes leather sandals in her workshop in Arusha. In one week, she worked with two assistants. Their combined data is:
- Total basic wages: TZS 120,000
- Overtime paid: TZS 15,000
- Transport allowance: TZS 10,000
- NSSF contribution by employer: TZS 13,500
- Total sandals produced: 50 pairs
Step 1: Calculate total labour cost
Total Labour Cost=120,000+15,000+10,000+13,500=TZS 158,500
Step 2: Calculate labour cost per pair of sandals
Labour Cost Per Unit=50158,500=TZS 3,170 per pair
If Mariam wants to make a profit, she must add material costs and her desired profit to TZS 3,170 when setting the selling price.
- Helps set accurate selling prices
- Shows where money is being spent
- Identifies waste or inefficiency
- Helps compare different workers or methods
- Supports decisions about hiring more workers or buying equipment
Often the market decides the price, so a producer works backwards to a target cost:
Target cost = expected selling price - desired profit
Suppose Mariam's sandals can sell at TZS 12,000 a pair and she wants a profit of TZS 2,000. Her target cost is 12,000 - 2,000 = TZS 10,000. If materials and overheads come to TZS 7,500 a pair, her total cost is 7,500 + 3,170 = TZS 10,670, which is TZS 670 above the target. She must look for savings, for example by training her assistants, arranging the workbenches better or keeping knives sharp so that each pair takes less time. Paying workers less than the legal minimum wage or skipping safety is not an acceptable saving.
Labour costs are only as accurate as the records behind them. Record each working day in an attendance register or time sheet, each wage payment in a wage book signed by the worker, and the totals in the cash book. Work carefully: a small mistake in hours or pay is repeated in every unit made. Costing information is used inside the business, to set prices and control costs, and outside it, by lenders and the tax authority.
Costing is office work, but safe habits still apply. Sit at a tidy desk with good light and keep computer and phone-charger cables off the floor. Follow all workshop safety rules when you go near machines to time a job. Afterwards, file the cost sheets and wage records safely, wipe the desk, clean and put away the calculator and other tools, and switch off the computer.
When Juma opens a small shoe repair shop in Mwanza, he needs to know his labour costs to charge customers fairly. If he spends TZS 8,000 on labour to repair five pairs of shoes in a day, his labour cost per repair is TZS 1,600. He must add the cost of leather patches, glue, and thread to this amount, plus his profit margin, to decide the final repair price for each customer.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Obtain the cost of materials
- Prepare materials specification sheet
- Prepare cost sheet
- Determine direct costs
- Determine indirect costs
- Determine overhead cost
- Record all business transactions
- Observe safety
- Clean workplace
- Clean work tools
Tathmini ya matokeo
Labour cost is done according to the financial principles, rules and regulations
Tathmini ya maarifa
Knowledge evidence:
Detailed knowledge of:
Method used: The student should explain how to:
- Analyse labor costs
Principles: The student should explain the principles of:
- Indirect and direct costing
- Labour cost calculations
- Target cost management
Theories: The student should explain:
- The relevance of costing information
- The internal and external dimensions of costing
- The integrated advanced cost management system features
- The importance of precision and attention to details when performing costing and estimating
Circumstantial knowledge:
Detailed knowledge of:
- Safe systems of work
- Safe work environment
Swali
Which of the following is NOT a component of labour cost?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado