- Preparing list of materials and items
- Calculating material cost
- Calculating labour and profit
Calculating Labour and Profit
When pricing a construction project, a mason must calculate not only the cost of materials but also the cost of labour and add a profit margin. Labour costs include wages for workers, while profit is the amount earned after all expenses are deducted. Accurate calculation of labour and profit ensures that a project is financially viable and that the mason earns a fair income.
Workers in construction projects are categorised based on their skills and responsibilities:
- Masons are skilled workers who lay bricks, blocks, or stones to construct walls and other structures. They ensure bricks are placed correctly and structures are stable.
- Assistants are unskilled or semi-skilled workers who support masons by mixing mortar, carrying materials, and preparing the work area.
- Supervisors oversee the construction process, manage workers, ensure quality standards, and coordinate tasks.
- Equipment operators handle machinery such as concrete mixers and lifting equipment.
Labour costs go beyond basic wages and include additional expenses:
- Wages are the regular pay received by workers for their work.
- Overtime pay is extra payment for workers who work beyond regular hours to meet deadlines.
- Allowances cover expenses such as travel, meals, or accommodation when the site is far from workers' homes.
- Benefits include contributions to social security, health insurance, or pensions as required by law.
To estimate labour costs, a mason must determine:
- The number of workers required
- The time needed to complete each task (productivity rate)
- The wage rate for each worker category
Worked Example: Labour for a 15m² Block Wall
A mason can lay 200 blocks per day, and an assistant can prepare mortar for 200 blocks per day. Wage rates are TZS 40,000 per day for a mason and TZS 15,000 per day for an assistant.
Step 1: Calculate total blocks required
- Assume 12 blocks per m² plus 10% waste
- Total blocks = 15m² × 12 blocks/m² × 1.10 = 198 blocks
- Round to 210 blocks for practical purposes
Step 2: Calculate labour days
- Mason's labour days = 210 blocks ÷ 200 blocks/day = 1.05 days
- Assistant's labour days = 210 blocks ÷ 200 blocks/day = 1.05 days
Step 3: Calculate total labour cost
- Mason: 1.05 days × TZS 40,000 = TZS 42,000
- Assistant: 1.05 days × TZS 15,000 = TZS 15,750
- Total labour cost = TZS 57,750
Overheads
Overheads are indirect costs that are not directly tied to materials or labour but are necessary for the project. These include:
- Transportation costs for delivering materials
- Tool and equipment costs
- Administrative costs
Overheads are usually calculated as a percentage of total material and labour costs (commonly 10%).
Profit
Profit is the contractor's earnings after deducting all expenses. It is usually calculated as a percentage of the total project cost (commonly 15%). Profit allows the mason to sustain their business and invest in future projects.
Formula for Total Project Cost:
Total Cost = Materials + Labour + Overheads + Profit
A Bill of Quantities (BOQ) is a document that lists all materials, labour, and costs required for a project. It includes:
- Item description
- Unit of measurement
- Quantity
- Unit rate
- Total cost
Structure of a BOQ
| Item | Description | Unit | Quantity | Unit Cost (TZS) | Total Cost (TZS) |
|---|---|---|---|---|---|
| Bricks | 230×110×75mm | Pieces | 825 | 150 | 123,750 |
| Cement | 50kg bag | Bags | 2 | 15,000 | 30,000 |
| Sand | Fine, washed | m³ | 0.32 | 30,000 | 9,600 |
| Labour (Mason) | Laying bricks | Days | 0.825 | 40,000 | 33,000 |
| Labour (Assistant) | Mixing mortar | Days | 0.825 | 15,000 | 12,375 |
| Overheads | Indirect expenses | - | - | - | 22,572.50 |
| Profit | Contractor's earnings | - | - | - | 37,739.63 |
| Total | 289,337.13 |
- Calculate total material costs
- Calculate total labour costs
- Add material and labour costs together
- Calculate overheads (e.g., 10% of material + labour)
- Calculate total cost including overheads
- Calculate profit (e.g., 15% of total cost)
- Add profit to get the final project price
In Tanzania, a mason who can accurately calculate labour and profit will be able to bid competitively for construction jobs. For example, when building a 10-metre boundary wall for a household in Dar es Salaam, the mason can calculate that they need 1 mason and 1 assistant for 2 days, add material costs of approximately TZS 800,000, add 10% overheads (TZS 80,000) and 15% profit (TZS 132,000), giving a total price of TZS 1,012,000. This ensures the mason earns a fair profit while offering a competitive price to the client.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Identify labor categories
- Determine labor rates
- Estimate labor hours
- Determine profit margin
- Document calculations
- Review and validate
Tathmini ya matokeo
Labor and profit are calculated as per standard methods of measurement to ensure a comprehensive understanding of project costs and financial viability
Tathmini ya maarifa
Detailed knowledge of:
Method used: The students should explain different procedures of calculating labour cost and profit
Principles: The student should explain the principles involved in calculating labour and profit
Theories: The student should explain:
- Cost-Benefit Analysis
- Costing procedures for Maximum profit
- Trade calculations
- Profit Maximization
- Economic Theory of Labor
Circumstantial knowledge: Detailed knowledge about:
- Safety precautions to be observed while performing tasks
- Value for money observed
Swali
Which of the following is NOT a labour category in masonry and bricklaying as mentioned in the lesson?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado