Mada za sehemu hiiPerforming cost estimatesMada 2
- Writing schedule of rates
- Preparing costing estimates
Writing Schedule of Rates
A schedule of rates is a document that lists the unit prices for different construction works or building items. It shows how much each type of work costs per unit of measurement, such as per square meter, per cubic meter, or per piece. Contractors, architects, and clients use this document to prepare cost estimates for building projects.
The schedule of rates serves several important purposes:
- Preparing estimates: It helps calculate the total cost of a building project before construction begins.
- Tendering: Contractors use it when submitting their price quotes (bids) for a project.
- Contract agreements: It forms part of the contract to value work done during construction.
- Cost control: It allows clients to monitor and control project expenses.
Each item in a schedule of rates should include:
- Item number – A reference number for each work item
- Description of work – Clear name of the construction activity (e.g., "Concrete work for foundation")
- Unit of measurement – The measurement basis (e.g., m², m³, kg, number)
- Material cost – Cost of raw materials needed for one unit
- Labor cost – Cost of workers' wages for completing one unit
- Equipment cost – Cost of machinery or tools used (if applicable)
- Overhead and profit – Additional percentage to cover indirect costs and profit
- Total unit rate – The final price per unit (sum of all costs plus overhead)
Step 1: Identify the Work Items
List all the construction activities that need pricing. Examples include:
- Excavation
- Concrete work
- Brickwork
- Plastering
- Roofing
Step 2: Determine the Unit of Measurement
Choose the appropriate unit for each item:
- Excavation is measured in cubic meters (m³)
- Brickwork is measured in square meters (m²)
- Concrete is measured in cubic meters (m³)
Step 3: Calculate Material Cost
Find the current market price of materials required for one unit of work. Include the cost of transporting materials to the site.
Step 4: Calculate Labor Cost
Determine how many labor hours are needed to complete one unit of work. Multiply the hours by the prevailing daily labor wage rate.
Step 5: Add Equipment Cost (if applicable)
If machinery is needed, include its cost per unit. This may include rental cost or depreciation.
Step 6: Add Overhead and Profit
Add a percentage (commonly 10% to 25%) to cover:
- Site office expenses
- Supervision costs
- Transport and logistics
- Contingencies
- Contractor's profit
Step 7: Calculate the Total Unit Rate
Use the formula:
Unit Rate=Material Cost+Labor Cost+Equipment Cost+Overhead and Profit
Item: Concrete work (1:2:4 mix) for foundation
Given:
- Cement: 7 bags required per m³ → 7 × TZS 12,000 = TZS 84,000
- Sand: 0.5 m³ required per m³ → 0.5 × TZS 25,000 = TZS 12,500
- Aggregate: 1.0 m³ required per m³ → 1.0 × TZS 35,000 = TZS 35,000
- Labor: 2 days required per m³ → 2 × TZS 15,000 = TZS 30,000
- Overhead and profit: 15%
Calculation:
| Description | Amount (TZS) |
|---|---|
| Material (Cement + Sand + Aggregate) | 84,000 + 12,500 + 35,000 = 131,500 |
| Labor | 30,000 |
| Subtotal | 161,500 |
| Add 15% Overhead and Profit | 161,500 × 0.15 = 24,225 |
| Total Unit Rate per m³ | 185,725 |
Therefore, the schedule of rates for concrete work (1:2:4 mix) is TZS 185,725 per cubic meter.
- Always use current market prices for materials and labor
- Check local suppliers and wage rates regularly
- Include wastage factors for materials (typically 5% to 10%)
- Use a spreadsheet (like Microsoft Excel) to organize calculations neatly
- Double-check all arithmetic before finalizing rates
In Tanzania, a schedule of rates is commonly used when a family wants to build a house. For example, if Mwalimu Juma in Dodoma wants to construct a three-bedroom house, a contractor will use the schedule of rates to calculate the total cost — pricing items like excavation per cubic meter, concrete work per cubic meter, and wall plastering per square meter. This helps Mwalimu Juma plan his budget and compare quotes from different contractors before starting construction.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Determine cost rate of an activity
- Fill cost rate as per activities column
Tathmini ya matokeo
A quantified list of work activities conforming to the estimating standards
Tathmini ya maarifa
Knowledge evidence:
Detailed knowledge of:
Method used: The student should explain how to build rates of a building work
Principles: The student should explain the principles of:
- Building an activity rate
- Building an activity cost
Theories: The student should explain:
- The elements constituting an activity rate
- The percentages of the elements that build rate Detailed knowledge about:
- Safety on handling of tools
- Accuracy of built rates
Swali
What is the primary purpose of a schedule of rates in building construction?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.