Mada za sehemu hiiWriting specificationsMada 2
- Writing a schedule of materials and symbols
- Writing a schedule of specifications
A schedule of specifications is a document that provides detailed descriptions of materials, dimensions, quantities, and quality standards required for construction work, working together with drawings to ensure everyone understands what materials and methods should be used.
Building specifications are very important in the construction process. They provide detailed descriptions of the materials, dimensions, quantities, and quality standards required for constructing a building or structure. These specifications make sure everyone involved in the project—from contractors to suppliers—understands what is expected in terms of materials, construction methods, and the quality of work.
Specifications are categorised as either "Closed" or "Open" in the tendering process:
- Closed specifications mean no other product can be used other than what is specifically stated.
- Open specifications allow substitution of the specified product with an equivalent one that meets the required performance quality.
Building specifications serve several important purposes:
- They define the scope of work and describe the requirements for project execution.
- They define and limit material fabrication methods.
- They help avoid misunderstanding by ensuring positive control of quality during construction.
- They help clarify information on the drawing during tendering, bidding, and the construction process.
In building construction, specifications and working drawings are used together. When there is conflicting information between the working drawings and specifications, the specifications take precedence over the working drawings.
- Working drawings show the relative position and proportion of various items of the structure.
- Specifications give specific details about each item by defining its type, physical characteristics including dimensions, colour, and surface finishes.
- Specifications also provide technical information like design details, operation requirements, material properties, and energy efficiency.
There are four main types of building specifications:
1. Prescriptive Specification
This specifies each product by name, equipment, and system to be used. It is the most restrictive (closed) type because the designer has full control over what is to be used. The products are prescribed by make name, model number, colour, or finish.
Example: "Union-Gower lock set J682-94-CH-2.5L as manufactured by Apex Trading and Services."
2. Descriptive Specification
This provides a written description of the material, equipment, construction systems, and the level of work quality required. It is an open specification that does not restrict brand names.
Example: "Sharp natural sand, free from salt, clean and well graded, passing a 35-mesh sieve and not more than 3% passing a 150-mesh sieve on screening."
3. Performance Specification
This sets forth the standard required for a given assembly, component, device, equipment, or material. It informs the contractor about the capability of the final installed product without telling them how to achieve the results. It is also an open specification that does not restrict brand names.
Example: "Exhaust fan performance: rated for continuous operation at the capacity of 15 m³/min against a static pressure of 1.27 cm of water column and temperature of 50°C."
4. Reference Specification
This specifies standards developed by standard-setting organisations. It is based on standards set by an established authority such as Tanzania National Standards (TZS) as developed by the Tanzania Bureau of Standards (TBS). It is an open specification that does not mention or restrict trade names or brands.
Example: "Unless otherwise specified on the drawings, the cement shall be ordinary Portland cement of approved manufacturers, delivered in the manufacturer's bags."
Specifications are legal documents. Their language must be precise, adequate, clear, and unambiguous. The following principles should be observed:
- Language: Use simple language and make sentences brief and clear.
- Writing format: Include table of contents, number of tables, page numbers, and definition of terms to avoid misinterpretations.
- Consistency: Observe consistent terminology, abbreviations, writing format, and arrangement of materials.
- Cross-reference: Use cross-references if items have previously been used in the project to avoid repeating details.
For effective results, consider these factors:
- Nature of works: Specifications vary depending on whether the work is for new construction, rehabilitation, or maintenance.
- Type of contract: Public projects should use open specifications (guided by procurement regulations), while private projects may be open or closed.
- Availability of technology and materials: Ensure that the specified material or technology is available.
Below is a simple example of a schedule of specifications for a guard room floor:
| Item | Specification |
|---|---|
| Wall | 150 mm thick masonry block wall, plastered and painted with 3 coats of high-grade wash and wear weather guard emulsion paint |
| Floor | 100 mm thick concrete floor slab with 40 mm terrazzo paving, polished smoothly |
| Ceiling | 12 mm thick gypsum board ceiling fixed with approved screws to suspended galvanized steel C-channel profiles |
| Door | 55 × 180 mm varnished hardwood (teak) frames, fitted with 6 mm clear glass fanlight |
| Window | 100 mm anodized aluminium frames, 38 mm sliding panels with 6 mm clear glass, frame thickness 2.0 mm |
In Tanzania, when a family wants to construct a house in places like Mwanza, Arusha, or Dodoma, they need a schedule of specifications to tell the contractor exactly what materials to use—such as the type of cement, size of steel bars, and quality of paint. This prevents disputes and ensures the building is strong and durable. For example, specifying "ordinary Portland cement from TBS-approved manufacturers" helps the owner get quality materials even when the contractor tries to use cheaper alternatives.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Select tools as per range statement
- Prepare paper format and title block layout
- Draw floor plan, drawings, section, and elevations
- Write dimensions
- Write/express correct material symbols on section drawings
- Write specifications on floor plan and section drawings
Tathmini ya matokeo
Written schedule of specification conforms to set standards
Tathmini ya maarifa
Knowledge evidence:
Detailed knowledge of:
Method used: The student should explain the methods involved in the writing of schedule of specifications
Principles: The student should explain the principles involved in:
- Writing schedule of specifications
Theories: The student should explain:
- Importance of writing schedule of specifications Circumstantial Detailed knowledge about:
- Handling of tools
- Storage of drawings (transparencies)
Swali
What is the main purpose of a schedule of specifications in building construction?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado