Carpentry and Joinery With Metal Works

Performing runner system

takriban dakika 5 kusoma

Majadiliano
Mada za sehemu hiiConstructing timbering to trenchMada 5

A runner system is a temporary support method used in trench excavation where the soil is so loose and soft that it requires immediate support as the work progresses. Unlike vertical sheeting, runner system uses long, thick wooden planks with iron shoes at the ends that are driven into the ground ahead of excavation.

What is a Runner System?

A runner system is a type of timbering used for deep trenches in loose or soft soil. It consists of runners—long, thick wooden sheets or planks with iron shoes (runners) at their lower ends—that are driven into the ground by hammering before excavation begins. This system provides immediate support to prevent trench collapse in unstable soils.

When is a Runner System Used?

The runner system is used when:

  • The soil is very loose and soft
  • There is risk of immediate collapse during excavation
  • The trench depth exceeds what stay bracing or box sheeting can safely support
  • Groundwater conditions cause soil instability
  • The soil requires support as excavation progresses, not after

Components of a Runner System

Runners: Long, thick wooden planks (approximately 200 mm × 75 mm) with iron shoes at the bottom end. They are placed vertically against trench walls and driven about 30 cm ahead of excavation progress.

Walers (Wales): Horizontal timber or steel beams (typically 150 mm × 100 mm) fixed across runners to distribute load. They connect opposite walls of the trench.

Struts or Trench Jacks: Horizontal members placed between opposite walers to brace the trench walls. They prevent inward movement of the walls.

Iron Shoes: Metal fittings attached to the bottom of runners to facilitate driving into hard ground and prevent splintering.

Procedure for Performing a Runner System

Step 1: Site Preparation and Safety Check

  • Check soil type and confirm it is loose soil
  • Assess ground stability and water table level
  • Mark trench location with pegs and string lines
  • Ensure all workers wear appropriate PPE (helmet, gloves, safety boots, goggles, reflective vest)
  • Conduct safety briefing

Step 2: Begin Excavation

  • Excavate in stages (1.2 to 1.5 m depth increments)
  • Keep trench sides as vertical as possible
  • Remove loose material carefully

Step 3: Place Runners

  • Position vertical timber runners against both trench walls
  • Place runners at 1.2 to 1.5 m intervals, depending on soil looseness
  • Drive runners into the ground by hammering, about 30 cm ahead of excavation progress

Step 4: Install Walers

  • Fix horizontal walers across runners on opposite trench walls
  • For a 6 m deep trench, use at least 3 levels (for example, at 2 m, 4 m, and near the bottom)
  • Ensure walers are properly aligned and tight

Step 5: Install Struts

  • Place horizontal struts or adjustable trench jacks across the trench
  • Position them between opposite walers
  • Ensure they are securely fitted and do not obstruct access

Step 6: Continue Excavation

  • Proceed with the next depth stage (approximately 1.5 m at a time)
  • Repeat runner, waler, and strut placement as excavation deepens

Step 7: Inspection

  • Check all components for tightness and alignment
  • Inspect for bowing runners, loose soil, or over-stressed struts
  • Ensure ladders and barriers are properly installed

Step 8: Dismantling

  • Remove supports in reverse order (top to bottom)
  • Remove struts first, then walers, then runners
  • Backfill gradually in 150–200 mm layers and compact

Worked Example

Activity: Install runner system for a foundation trench 1.5 m wide and 6.0 m deep in loose soil.

Given:

  • Trench width: 1.5 m
  • Trench depth: 6.0 m
  • Soil condition: Loose
  • Runner spacing: 1.5 m apart (two sides of trench)

Calculations:

If trench length is 8 m, the number of runners needed on each side: Number of runners=trench lengthspacing+1=81.5+1≈6+1=7 runners per sideNumber\ of\ runners = \frac{trench\ length}{spacing} + 1 = \frac{8}{1.5} + 1 \approx 6 + 1 = 7\ runners\ per\ side

For a 6 m deep trench with walers at 3 levels (at 2 m, 4 m, and 5.5 m from top):

  • Total walers needed: 3 levels × 2 walls = 6 walers
  • Struts: placed at each waler level across the 1.5 m width

Safety Considerations

  • Always wear PPE: helmet, safety boots, gloves, goggles, and high-visibility vest
  • Never enter an unsupported trench
  • Check for water seepage regularly—stop work if water inflow increases
  • Inspect all components before each work shift
  • Maintain proper access ladders
  • Install warning signage and barriers
  • Evacuate immediately if signs of instability appear (cracking sounds, bowing walls, water seeping rapidly)

Common Challenges and Solutions

Water Seepage: If water begins seeping into the trench, install drainage or pumping system immediately. Reduce excavation depth increments and increase support frequency.

Cracked Soil: If soil cracks develop despite installed support, stop work and evacuate. Add additional struts and walers. Consider changing to a more robust support system.

Runner Bowing: If runners begin to bow inward, this indicates overloading. Add additional struts or reduce spacing between runners.

Real-life application

In Tanzania, a builder in Dar es Salaam or Arusha constructing a foundation for a house or commercial building often encounters loose sandy soil, especially near rivers or in low-lying areas. When excavating deep foundations for water tanks, septic tanks, or underground service ducts, the runner system provides essential temporary support to prevent trench collapse, protecting workers and ensuring construction proceeds safely. A small-scale contractor can apply this knowledge to bid for foundation works and charge for trench support installation as an additional service, earning extra income during building projects.

Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa

Tathmini ya mchakato

The student should be able to:

  • Interpret drawings
  • Calculate materials required
  • Prepare ribs
  • Prepare laggings
  • Fix lagging to ribs
  • Erect and reinforce centering
  • Dismantling centering
  • Clean work place and tools
  • Store tools to safe place

Tathmini ya matokeo

Performed runner system conform technical specifications

Tathmini ya maarifa

Detailed knowledge of:

Method used: The student should explain how to construct a runner system

Principles: The student should explain principles related to constructing runner system

Theories: The students should explain uses of runner system

Circumstantial knowledge: The students should explain detailed knowledge related to maintain workshop safety rules and regulations

Swali

What is the main purpose of a runner system in trench excavation?

Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.

Ingia ili kufanya mazoezi

Mwalimu

Umekwama? Niulize chochote kuhusu mada hii.

Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.

Ingia ili kuuliza

Majadiliano

Hakuna maswali bado

Ingia ili kuuliza
Inapakia majadiliano…