Taking Readings and Booking in Survey Works

Taking readings and booking is the process of measuring heights and distances on a survey site and recording them systematically for later calculation and plan preparation. In construction and civil engineering, accurate readings form the foundation for setting out buildings, roads, and other structures. This skill combines the proper use of surveying instruments with careful data recording to ensure reliable survey results.

When performing a levelling survey, you will encounter three main types of staff readings:

Backsight (BS) — This is the first reading taken after setting up the instrument, always on a point of known elevation (such as a benchmark). The backsight reading is added to the known elevation to determine the height of instrument.

Intermediate Sight (IS) — These are readings taken on points between the backsight and foresight where elevation data is needed but where the instrument will not be moved. Multiple intermediate sights can be recorded in a single setup.

Foresight (FS) — This is the final reading taken before moving the instrument to a new position. It marks the transition point and is always the last reading recorded before instrument relocation.

How you'll be assessedProcess assessment · Outcome assessment · Knowledge assessment

Process assessment

The student should be able to:

  • Select surveying instrument
  • Search for boundary markers (metal stakes, concrete posts, etc.) as described in the survey plan
  • Use a GPS device to identify coordinates of known points
  • Identify alternative reference points if markers are missing or damaged
  • Measure distances and angles between boundary markers using a total station or theodolite
  • Compare field measurements to those in the existing survey plan
  • Mark the boundaries with visible stakes or flags for clarity
  • Use a compass or total station to verify directional bearings between boundary points
  • Record observations
  • Document any discrepancies between the survey plan and actual field conditions
  • Clean tools and store them

Outcome assessment

Surveyed site boundaries conforming to technical specifications.

Knowledge assessment

Knowledge evidence:

Detailed knowledge of:

Method used: The Student should explain different ways of:

  • Taking readings
  • Booking readings
  • Set out angles
  • Computing methods

Principles: The student should explain the different principles of:

  • Taking and booking reading
  • Surveying terminologies

Theories: The student should explain: instruments

  • Set and reading Instruments
  • Set angles
  • Set straight lines
  • Care of Detailed knowledge about:
  • Safety precautions related to surveying instruments
  • Environmental issues
  • First aid

Question

Which type of staff reading is taken first after setting up the levelling instrument on a point of known elevation?

Sign in to submit your answer and have it count toward your mastery.

Sign in to practice

Tutor

Stuck? Ask me anything about this topic.

Sign in to ask the Sonza AI Tutor about this question.

Sign in to ask

Discussions

No questions yet

Sign in to ask
Loading discussions…