Analysing data by HI and RF

about 5 minutes to read

Discussions
Topics in this sectionPerforming site survey5 topics

Analysing Levelling Data by HI and RF Methods

In surveying, after taking staff readings at different points, we must reduce the data to find the Reduced Level (RL) of each point. This is done using either the Height of Instrument (HI) method or the Rise and Fall (RF) method. Both methods give the same results if done correctly.


  • Back Sight (BS): The first staff reading taken after setting up the instrument, always on a point of known RL (usually a Benchmark).
  • Intermediate Sight (IS): Any staff reading taken on points whose RL we want to determine (not BS or FS).
  • Fore Sight (FS): The last staff reading taken before moving the instrument to a new station.
  • Reduced Level (RL): The elevation of a point above or below the datum (sea level).
  • Benchmark (BM): A point of known RL used as a reference.
  • Height of Instrument (HI): The RL of the instrument axis after the level is set up.

How you'll be assessedProcess assessment · Outcome assessment · Knowledge assessment

Process assessment

The student should be able to:

  • Set the Benchmark (BM)
  • Determine the Height of Instrument (HI)
  • Calculate Reduced Levels (RL)
  • Repeat for Intermediate Points
  • Document in a Levelling Table
  • Calculate the Rise or Fall
  • Clean tools and store them

Outcome assessment

Surveyed site conforms to technical specifications

Knowledge assessment

Knowledge evidence:

Detailed knowledge of:

Method used: The student should explain different ways of:

  • Taking readings
  • Booking readings
  • Set out angles
  • Computing methods

Principles: The student should explain the different principles of:

  • Setting levelling instruments
  • Taking and booking reading
  • Surveying terminologies

Theories: The student should explain:

  • Set and reading
  • Instruments
  • Booking and calculating
  • Reduced levels
  • Set angles
  • Set straight lines
  • Transferring
  • Care of Detailed knowledge about:
  • Safety precautions related to surveying instruments
  • Environmental issues
  • First aid

Question

In levelling surveys, what does the abbreviation BS stand for?

Sign in to submit your answer and have it count toward your mastery.

Sign in to practice

Tutor

Stuck? Ask me anything about this topic.

Sign in to ask the Sonza AI Tutor about this question.

Sign in to ask

Discussions

No questions yet

Sign in to ask
Loading discussions…