Mada za sehemu hiiDesigning and making liquid coolersMada 5
- Designing and draw schematic diagram
- Making juice cooler body
- Installing refrigerant pipe circuit
- Installing electrical wiring circuits
- Charging and commissioning the system
Installing Refrigerant Pipe Circuit
A refrigerant pipe circuit is the network of tubes that connects the compressor, condenser, evaporator, and other components in a refrigeration system, allowing the refrigerant to circulate and transfer heat. Installing the pipe circuit correctly is essential for the system to work efficiently and safely, as any leaks or poor connections can cause cooling failure or dangerous pressure buildup.
Step 1: Planning and Measuring
Before cutting any pipes, plan the layout of the pipe circuit on paper. Measure all distances carefully using a tape measure, and mark the pipe lengths needed for each section—suction line, liquid line, and discharge line. Accurate measurements prevent waste of materials and ensure proper flow of refrigerant.
Step 2: Cutting and Deburring
Cut the copper pipes to the required lengths using a pipe cutter or shearing machine. After cutting, remove any sharp edges or burrs from the inside of the pipe using a reaming tool or deburring tool. Smooth edges prevent damage to the pipe walls and ensure good flow.
Step 3: Bending the Pipes
Use a bending machine to form the necessary bends in the pipe runs. Bends should be smooth and gradual; sharp bends restrict refrigerant flow and cause pressure losses. Maintain the proper bend radius as specified in the system design.
Step 4: Flaring and Fitting
Create flared ends on the pipes where they will connect to components or other pipes. Use a flaring tool to expand the pipe end at a 45-degree angle. Apply appropriate fittings—couplings, elbows, tees—and secure them withflare nuts.
Step 5: Joining and Brazing
Join the pipe sections using the correct method. For copper-to-copper joints, use silver brazing or hard soldering with an oxy-acetylene plant. Heat the joint evenly, apply the brazing alloy, and allow it to flow into the gap. Ensure leak-free joints.
Step 6: Installing Supports and Insulation
Mount the pipes securely to the framework using brackets or clamps. Install appropriate insulation on suction lines to prevent heat gain and condensation. Secure all connections and check for proper support throughout the run.
Step 7: Testing for Leaks
After installation, pressurize the system with dry nitrogen to test for leaks. Use a leak detection spray or electronic leak detector around all joints and connections. Repair any leaks found before charging the system with refrigerant.
- Tape measure for accurate measurements
- Pipe cutter or shearing machine for cutting
- Deburring tool for removing sharp edges
- Bending machine for forming smooth bends
- Flaring tool for creating flared connections
- Oxy-acetylene plant for brazing and soldering
- Soldering gun for smaller joints
- Leak detection equipment for testing
- Safety goggles, gloves, and protective clothing
- Always wear safety goggles and gloves when cutting, bending, or brazing pipes
- Ensure good ventilation when using oxy-acetylene or soldering equipment
- Never work on pipes under pressure—always release refrigerant safely first
- Keep a fire extinguisher nearby when using open flames
- Secure cylinders of acetylene and oxygen upright and away from heat sources
A technician needs to install the refrigerant pipe circuit for a domestic refrigerator. The suction line must run 1.5 meters from the evaporator to the compressor, with two 90-degree bends. The liquid line runs 0.8 meters from the condenser to the evaporator, with one bend.
Solution:
- Measure and cut 1.5 m of copper pipe for the suction line and 0.8 m for the liquid line
- Deburr both cut ends to remove sharp edges
- Use the bending machine to form two smooth 90° bends in the suction line and one bend in the liquid line
- Create flared ends on both pipes using the flaring tool
- Braze the connections to the evaporator, compressor, and condenser using the oxy-acetylene plant
- Install insulation on the suction line and mount all pipes securely
- Pressurize the system with dry nitrogen to 1.5 MPa and check for leaks using leak detection spray
The system passes the leak test and is ready for charging with refrigerant R-134a.
In Tanzania, refrigeration technicians who master pipe circuit installation are employed in air conditioning repair shops, cold storage facilities for fish and vegetables at markets like Kariakoo in Dar es Salaam, and hotels that need reliable air conditioning. A technician who can properly install and leak-test refrigerant pipes can start a small business charging and repairing refrigerators and air conditioners, earning between TZS 50,000 to TZS 150,000 per service call in urban areas.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The students should be able to:
- Select materials, tools and equipment
- Draw detailed drawing and assembly drawings
- Draw electrical wiring circuits
- Prepare the system main body structures of the liquid coolers
- Mount the refrigerating compound in the case
- Make a refrigerating cabinet body and cooling coil
- Perform wiring circuits for both heating and cooling
- Perform spray painting
- Apply safety gears
- Clean workplace, tools and equipment
- Store tools and equipment
- Commission the system performance
Tathmini ya matokeo
Designed and made liquid coolers conform to the technical specifications and aesthetic appearance
Tathmini ya maarifa
Knowledge Evidence:
Detailed knowledge of:
Method used: The student should explain how to:
- Make different kind of coolers
- Apply safety measures
Principles: The student should explain the principles of: (c) Heat transfer and exchange (d) Design characteristics/parameters
Theories: The student should explain:
- The functional of components
- Refrigeration cycle
- Heat load estimation/calculations
Circumstantial knowledge:
Detailed knowledge about:
- Safe handling of tools, equipment and machines
- Environmental regulations
Swali
What is the first step in installing a refrigerant pipe circuit?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado