Mada za sehemu hiiConstructing archesMada 3
- Setting arches
- Making centering for arches
- Constructing different types of arches
Arches are curved structural elements that span openings like doors and windows, transferring the weight above the opening to the sides (abutments) without using flat beams. Unlike lintels, arches use their curved shape to distribute loads efficiently, making them stronger and allowing for wider openings. Arches also add decorative value to buildings, which is why they are common in both traditional and modern Tanzanian construction.
Understanding arch terminology is essential for proper construction. Each part has a specific structural role:
- Abutment: The end support of an arch; the wall or pier that carries the thrust
- Intrados: The inner curve or surface of the arch
- Extrados: The outer curve or surface of the arch
- Voussoirs: Wedge-shaped stones or bricks that form the arch
- Springing stone: The first voussoir at the springing level on either side
- Springing line: An imaginary line joining the two springing points
- Crown: The highest point of the extrados
- Keystone: The central wedge-shaped block at the crown; locks all voussoirs in place
- Span: The clear horizontal distance between the inner faces of the supports
- Rise: The vertical distance from the springing line to the crown
- Haunch: The portion of the arch between the key and springing point
Arches are classified in three main ways:
By Material
- Masonry arch: Built from individual brick or stone units
- Concrete arch: Made from reinforced concrete
- Steel arch: Constructed from steel beams for large spans
- Wooden arch: Used in traditional or lightweight structures
By Shape
- Semicircular arch: The curve is a half-circle; the centre lies on the springing line
- Segmental arch: A shallow curve less than a semicircle
- Gothic (pointed) arch: Formed by two intersecting curves meeting at a pointed apex
By Number of Centres
| Type | Description |
|---|---|
| One-centred | Flat, segmental, circular, horseshoe |
| Two-centred | Pointed arches (equilateral, isosceles) |
| Three-centred | Semi-elliptical, Florentine, Ogee |
| Four-centred | Venetian, Tudor |
| Five-centred | Semi-elliptical |
Setting arches involves laying out the arch's shape, dimensions, and position before construction. The process requires accurate measurements and geometric calculations.
Steps for Setting Out an Arch
- Determine the span (width) and rise (height) from the design
- Mark the vertical centreline using a chalk line
- Locate and mark the springing points (half the span from centre on each side)
- Calculate the radius using the appropriate formula
- Draw the curve using a compass or trammel
- Create a template from plywood or cardboard
- Divide the curve into equal segments to mark voussoir positions
- Transfer the design to the construction surface
A segmental arch has a span (S) of 4 metres and a rise (H) of 1 metre. Calculate the radius (R) of the arch curve.
Using the formula from the textbook:
R=8HS2+2H
Substituting the values:
R=8×142+21
R=816+0.5
R=2+0.5
R=2.5 metres
Therefore, the radius of the segmental arch is 2.5 metres.
Centring is the temporary wooden framework that supports the arch during construction. It holds the voussoirs in position until the keystone is placed and the mortar sets.
Key Points About Centring
- Made from timber due to its adaptability and reusability
- Must be precisely shaped to match the arch's curve
- Requires strong bracing to prevent movement
- Should be removed only after mortar has fully cured
Procedure for Making Centring
- Determine the arch shape and size
- Create a template for the curve using a compass
- Construct a sturdy base frame with timber supports
- Cut planks or plywood to match the curve
- Assemble curved pieces onto the frame
- Add vertical and diagonal supports underneath
- Use props or shims to fine-tune alignment
- Verify with a spirit level before use
General Construction Steps
- Determine the appropriate arch type based on span and load
- Erect centring to support the arch during construction
- Lay voussoirs starting from springing points, working upward
- Place the keystone last to lock all units together
- Allow mortar to set and cure
- Remove the centring carefully when self-supporting
Constructing a Segmental Arch (Practical Steps)
- Clear and level the working area
- Measure and confirm the span and rise
- Mark the arch curve on plywood using the radius method
- Cut the segmental formwork
- Fix vertical supports to create stable centring
- Position the formwork in the opening; ensure it is level and aligned
- Lay mortar at the springing points
- Place voussoirs on both sides simultaneously for symmetry
- Work upward evenly, checking alignment with a spirit level
- Tap bricks gently to ensure full bedding
- Place the keystone to lock all voussoirs
- Check plumb and level of the arch
- Allow curing for 24–48 hours
- Remove the formwork carefully
- Inspect for stability and correctness
Materials Used in Arch Construction
- Stone: Traditional for smaller arches; durable
- Brick: Common for smaller spans; requires good quality
- Concrete: Modern material for reinforced arches
- Steel: Used with concrete for large-span arches
- Wood: Mainly for formwork and temporary support
Key Considerations
- Load distribution: The arch must handle the intended weight
- Aesthetics: Shape should match the architectural style
- Material selection: Balance durability, strength, and appearance
- Formwork: Must be robust, true to line and level, and stiff enough to resist deformation
In Tanzania, arches are commonly seen in school buildings, mosques, and traditional houses in regions like Stone Town, Zanzibar. When a mason in Mwanza needs to build a wider window opening for better ventilation in a shop, they may choose a segmental arch instead of a concrete lintel because arches distribute weight more efficiently and add attractive architectural character. A local builder applying these skills would first calculate the arch radius using the formula R=S2/8H+H/2 to ensure the curve supports the wall above, then construct proper centring before laying the brick voussoirs.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Interpret drawings
- Prepare materials
- Prepare tools and equipment
- Prepare form work
- Mix materials
- Cast the arche
- Fix the arches
- Perform curing
- Dismantle the form work
- Clean the work area and store tools
Tathmini ya matokeo
Different types of arches are constructed as per technical specifications to meet architectural requirements and structural demands
Tathmini ya maarifa
Detailed knowledge of:
Method used: The student should explain different ways of constructing arches
Principles: The student should explain the principles involved in constructing different types of arches
Theories: The student should explain:
- Types of arches
- Why prefer arches in bridging into wall opening
- Materials and their properties
- Tools and specific functions
- Importance of curing Circumstantial knowledge:
Detailed knowledge about:
- Safety precautions to be observed while constructing arches
- Environmental issues
- First aid
Swali
What is the springing line of an arch?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado