Mada za sehemu hiiPerforming site surveyMada 5
- Determining boundaries
- Determining benchmark and beacon
- Taking readings and booking
- Booking levelling readings
- Analysing data by HI and RF
Benchmarks and Beacons in Site Surveying
When construction workers build a house, a road, or any structure, they need fixed reference points on the ground that tell them where to dig, where to place walls, and how high to build. These reference points are called benchmarks and beacons. A benchmark gives a precise height (elevation), while a beacon marks a specific position or corner on the site. Together, they ensure that a building is level, straight, and in the correct position.
A benchmark (BM) is a fixed point with a known elevation above sea level. It serves as the reference point from which all other heights on a construction site are measured. Surveyors use benchmarks to make sure floors, walls, and foundations are level.
Types of Benchmarks
-
Permanent Benchmark – A long-lasting point established by a government survey department. In Tanzania, the Department of Survey and Mapping sets these along roads and major landmarks. These are used for large-scale projects.
-
Temporary Benchmark – A point established by the surveyor at the start of a project. It may be a metal pin, a nail, or a marked point on a permanent structure like a concrete wall.
-
Arbitrary Benchmark – A point assumed to have an elevation of 0.00 m or any convenient value when no known benchmark is nearby.
A beacon is a visible marker that identifies a specific point on the site, such as a corner of a building, the centerline of a road, or the boundary of a plot. Beacons are usually made of wooden stakes, concrete pillars, or metal pins driven into the ground.
Beacons show the exact location where construction work must begin and the boundaries that must not be crossed.
The following tools are needed to determine benchmarks and beacons:
- Levelling instrument (automatic level or dumpy level) – measures height differences
- Levelling staff – a graduated rod read through the level
- Measuring tapes – measure horizontal distances
- Ranging poles – straight poles used to sight alignment
- Set square – ensures right angles
- Chains – measure longer distances
- Club hammer – drives stakes into the ground
- Helmet – protects the worker
Step 1: Locate an Existing Benchmark
Start by finding a nearby permanent benchmark. In Tanzania, these are often marked on maps or found near government offices, schools, or road posts. If none is available, establish an arbitrary benchmark on a stable object.
Step 2: Set Up the Levelling Instrument
Place the level on a tripod at a position where you can see both the known benchmark and your work area. Level the instrument carefully using the adjusting screws.
Step 3: Take a Back Sight
With the staff held on the known benchmark, look through the level and record the reading. This is the back sight (BS).
Step 4: Take a Fore Sight
Move the staff to the point where you want to establish the new benchmark. Take a fore sight (FS) reading.
Step 5: Calculate the New Elevation
Use the formula:
New BM elevation=Known BM elevation+BS−FS
Step 6: Mark the New Benchmark
Drive a stake or mark a permanent point at the new benchmark location. Write the elevation clearly on a tag attached to the stake.
A surveyor finds a permanent benchmark with an elevation of 245.500 m. The back sight reading on this benchmark is 1.850 m. The surveyor moves the level and takes a fore sight of 1.200 m at a point where a new benchmark is needed.
Calculate the elevation of the new benchmark:
New BM elevation=245.500+1.850−1.200=246.150 m
The new benchmark is at 246.150 m above sea level.
Step 1: Review the Site Plan
Study the drawings to identify all points that need beaconing – corners, boundaries, and centerlines.
Step 2: Measure Distances
Using a tape or chain, measure distances from a known reference point (like an existing beacon or boundary corner) to the location of the new beacon.
Step 3: Set Out Right Angles
Use a set square or the 3-4-5 method to ensure angles are exactly 90° where required. Measure 3 m along one line, 4 m along the perpendicular line; the diagonal should measure 5 m.
Step 4: Drive the Beacon
At the exact measured point, drive a wooden stake (beacon) into the ground using a club hammer. The top of the stake should be level with the ground or slightly above.
Step 5: Verify Position
Sight through ranging poles to confirm the beacon aligns with other points on the site. Double-check all measurements before proceeding.
- Always wear a helmet on the survey site.
- Check that the levelling instrument is stable on its tripod.
- Beware of traffic or ongoing construction activities nearby.
- Handle the club hammer carefully to avoid injury when driving stakes.
In Tanzania, when a family builds a new house in Mwanza or Arusha, a surveyor first determines a benchmark from a nearby road marker to ensure the floor height avoids flooding, then places beacons at the four corners of the house so the builders know exactly where to dig the foundations and pour the concrete. This prevents costly mistakes, such as a crooked wall or a floor that is too low, which is especially important in areas with seasonal heavy rains.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Identify boundary markers or monuments mentioned in the plan
- Establish temporary bench marks
Tathmini ya matokeo
Bench marks and beacons are determined according to requirements
Tathmini ya maarifa
Knowledge evidence:
Detailed knowledge of:
Method used: The student should explain different ways of:
- Determining beacons and bench marks of a site
Principles: The student should explain the different principles of:
- Taking and booking reading
- Surveying terminologies
Theories: The student should explain:
- Meaning of benchmarks and
- Importance of
- Care of instruments Detailed knowledge about:
- Safety precautions related to surveying instruments
- Environmental issues
- First aid
Swali
What is the primary purpose of a benchmark in construction surveying?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado