Mada za sehemu hiiPerforming site surveyMada 5
- Determining boundaries
- Determining benchmark and beacon
- Taking readings and booking
- Booking levelling readings
- Analysing data by HI and RF
Taking Readings and Booking in Survey Works
Taking readings and booking is the process of measuring heights and distances on a survey site and recording them systematically for later calculation and plan preparation. In construction and civil engineering, accurate readings form the foundation for setting out buildings, roads, and other structures. This skill combines the proper use of surveying instruments with careful data recording to ensure reliable survey results.
When performing a levelling survey, you will encounter three main types of staff readings:
Backsight (BS) — This is the first reading taken after setting up the instrument, always on a point of known elevation (such as a benchmark). The backsight reading is added to the known elevation to determine the height of instrument.
Intermediate Sight (IS) — These are readings taken on points between the backsight and foresight where elevation data is needed but where the instrument will not be moved. Multiple intermediate sights can be recorded in a single setup.
Foresight (FS) — This is the final reading taken before moving the instrument to a new position. It marks the transition point and is always the last reading recorded before instrument relocation.
Booking refers to the systematic recording of all readings in a field book. Two common methods exist:
Height of Collimation Method
In this method, the height of the instrument (collimation) is calculated first, then used to find reduced levels of all points:
Height of Instrument (HI)=Benchmark Elevation+Backstaff Reading
Reduced Level (RL)=HI−Staff Reading
Rise and Fall Method
This method compares each reading to the previous one to determine whether the point is higher or lower:
Rise=Previous Reading−Current Reading Fall=Current Reading−Previous Reading
Reduced Level=Previous RL±Rise/Fall
-
Set up the levelling instrument on stable ground, approximately equidistant between the benchmark and the points to be surveyed. Ensure the instrument is level using the foot screws and bull's eye level.
-
Take the backsight on the benchmark or known point. Record this reading in the Backsight (BS) column of your field book.
-
Calculate the height of instrument by adding the backsight reading to the known benchmark elevation.
-
Take intermediate sights on all required points, recording each in the Intermediate Sight (IS) column. Calculate each point's reduced level by subtracting the staff reading from the height of instrument.
-
Take the foresight on the turning point, record it in the Foresight (FS) column, and calculate its reduced level.
-
Check arithmetic using the "closing error" — the difference between the calculated foresight elevation and the known benchmark elevation should be minimal (typically within tolerance).
A survey was conducted at a school construction site using a dumpy level. The benchmark (BM) has an elevation of 100.000 m. The following staff readings were taken and recorded:
| Station | BS (m) | IS (m) | FS (m) | HI (m) | RL (m) |
|---|---|---|---|---|---|
| BM | 1.850 | — | — | 101.850 | 100.000 |
| A | — | 1.420 | — | — | 100.430 |
| B | — | 0.985 | — | — | 100.865 |
| C | — | 2.100 | — | — | 99.750 |
| TP1 | — | — | 1.225 | — | 100.625 |
Calculations:
From BM: HI=100.000+1.850=101.850 m
Point A: RL=101.850−1.420=100.430 m
Point B: RL=101.850−0.985=100.865 m
Point C: RL=101.850−2.100=99.750 m
Turning Point 1: RL=101.850−1.225=100.625 m
- Always write readings in metres to three decimal places (millimetre accuracy)
- Record all entries clearly and in permanent ink
- Never erase errors — draw a single line through incorrect entries and write the correct value above
- Complete all calculations on site before moving to the next area
- Ensure the staff is held vertically by the assistant; tilting causes incorrect readings
When conducting survey work in Tanzania, always wear a helmet on construction sites. Ensure ranging poles and staff are held stable in windy conditions. When working near roads, wear high-visibility clothing and position team members to warn of approaching vehicles.
In Tanzania, taking readings and booking is essential for building contractors preparing foundation levels for houses, schools, or market stalls. For example, a contractor at a construction site in Mwanza must verify that the foundation concrete is poured at the correct elevation by taking level readings from a benchmark and booking the staff positions to calculate whether the slab height matches the design specification of 102.500 m above sea level.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Select surveying instrument
- Search for boundary markers (metal stakes, concrete posts, etc.) as described in the survey plan
- Use a GPS device to identify coordinates of known points
- Identify alternative reference points if markers are missing or damaged
- Measure distances and angles between boundary markers using a total station or theodolite
- Compare field measurements to those in the existing survey plan
- Mark the boundaries with visible stakes or flags for clarity
- Use a compass or total station to verify directional bearings between boundary points
- Record observations
- Document any discrepancies between the survey plan and actual field conditions
- Clean tools and store them
Tathmini ya matokeo
Surveyed site boundaries conforming to technical specifications.
Tathmini ya maarifa
Knowledge evidence:
Detailed knowledge of:
Method used: The Student should explain different ways of:
- Taking readings
- Booking readings
- Set out angles
- Computing methods
Principles: The student should explain the different principles of:
- Taking and booking reading
- Surveying terminologies
Theories: The student should explain: instruments
- Set and reading Instruments
- Set angles
- Set straight lines
- Care of Detailed knowledge about:
- Safety precautions related to surveying instruments
- Environmental issues
- First aid
Swali
Which type of staff reading is taken first after setting up the levelling instrument on a point of known elevation?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado