Mada za sehemu hiiConstructing timber stairsMada 3
- Constructing straight flight stair
- Constructing quarter turn stair
- Constructing half turn stair
A half turn stair (also called a quarter turn stair) is a type of straight-flight stair that changes the direction of travel by 90° using an intermediate landing or a winding section. This design is commonly used in Tanzanian buildings where space is limited and the stair must turn to fit the building layout.
Understanding the terminology helps you follow construction drawings and instructions accurately:
- Tread – the horizontal board that you step on
- Riser – the vertical board between two treads
- Stringer – the inclined timber beam that supports the treads and risers (also called carriage)
- Newel post – the thick vertical post at the bottom, top, and landing that supports the handrail
- Landing – the flat platform where the stair turns 90°
- Handrail – the horizontal or sloping rail for holding while climbing
- Baluster – the small vertical post between the handrail and the landing or tread
Before starting construction, gather these tools and safety gear:
- Tape measure, try square, and marking gauge
- Hand saws (crosscut and rip saw)
- Chisels and mallet
- Bench planes for smoothing surfaces
- Claw hammer and cramp (clamp)
- Drill or brace for boring holes
- Spirit level for checking horizontal and vertical surfaces
- Painting brush for applying preservative
- Safety boots, helmet, and overalls
1. Read and Understand the Drawing
Study the stair plan and section drawings to determine:
- Total rise (vertical height from floor to floor)
- Number of treads and risers
- Width of the stair
- Position of the landing
- Sizes of stringers, treads, and risers
2. Calculate the Rise and Run
The total rise is the vertical distance from the finished floor level (FFL) of the lower floor to the FFL of the upper floor. Divide this by the number of risers to get the unit rise (height of each riser).
The total run is the horizontal length of the stair from the bottom riser to the landing. Divide by the number of treads to get the unit run (depth of each tread).
In Tanzania, standard practice keeps the unit rise between 150 mm and 190 mm, and the unit run between 250 mm and 300 mm for comfortable climbing.
3. Mark Out the Stringers
- Place a long straight timber (the stringer) on sawing stools or a work bench.
- Using a try square and marking gauge, mark the position of each riser and tread along the top edge of the stringer.
- The top of each riser meets the bottom of the next tread above it.
- For a half turn stair, the stringer continues straight to the landing, then a second stringer begins from the landing and turns 90° to complete the upper flight.
4. Cut the Stringers
- Use a hand saw to cut along the marked lines.
- Cut the vertical lines first (for risers), then the horizontal lines (for treads).
- Smooth all cut surfaces with a bench plane to remove splinters and ensure tight joints.
5. Prepare the Treads and Risers
- Cut treads to the required width plus any overhang (usually 25 mm to 35 mm).
- Cut risers to the required height.
- Plane all surfaces smooth.
- Apply a suitable wood preservative using a painting brush to protect against insects and moisture.
6. Assemble the First Flight
- Fix the bottom newel post to the floor using bolts or screws.
- Position the stringers at the correct spacing (usually equal to the stair width minus two times the stringer thickness).
- Nail or screw the treads to the stringers, ensuring they are level (check with spirit level).
- Fit the risers between the treads, tight against the back of the upper tread.
7. Construct the Landing
- Build a platform at the required level, typically supported by timber joists or a brick wall.
- Ensure the landing is perfectly level in both directions.
- Install the landing newel post to support the handrail.
8. Assemble the Second Flight
Repeat the same process as the first flight, starting from the landing and turning 90° to reach the upper floor.
9. Install Handrails and Balusters
- Cut and fix the handrail to the newel posts at a comfortable height (usually 900 mm to 1000 mm above the nosing of the treads).
- Space balusters evenly (not more than 100 mm apart for safety).
- Secure all joints with nails or screws.
A classroom building in Dodoma has a total rise of 2,700 mm from the ground floor to the first floor. The architect specifies 15 risers for the half turn stair.
Calculate the unit rise: Unit rise=152700 mm=180 mm
If the landing is placed after 8 treads, the first flight has 8 treads and 9 risers (including the riser to the landing). The second flight has the remaining treads.
First flight:
- Number of treads = 8
- Number of risers = 9
- Total run = 8 × 280 mm = 2,240 mm (assuming unit run = 280 mm)
Second flight:
- Number of treads = 7
- Number of risers = 8
- Total run = 7 × 280 mm = 1,960 mm
The landing must be at the same level as the top of the 8th riser, creating a 90° turn. The carpenter marks these dimensions on the stringers, cuts accurately, and assembles the stair with treads, risers, newel posts, and handrail.
- Always wear safety boots, helmet, and overalls on the construction site.
- Use sharp chisels and saws carefully; keeptools in good condition.
- Secure the ladder or working platform before climbing.
- Check all joints are tight and the structure is stable before use.
- Keep the work area clean to avoid tripping over tools or offcuts.
In Tanzania, half turn stairs are frequently constructed in school buildings, dispensaries, and private homes where the building layout requires the stairs to change direction to fit available space. For example, a hardware shop owner in Mwanza needing to add a storage loft above the shop can build a half turn stair with a landing to save floor space while allowing customers or workers to climb comfortably with materials.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Interpret working drawings
- Calculate materials required
- Select tools and equipment
- Set height to the first floor
- Calculate total rise and total going
- Prepare string handrail and balustrades
- Fixing rises and goings
- Apply finishes
- Clean work place
- Store tools to safe place
Tathmini ya matokeo
Half turn stair conforms to technical specifications
Tathmini ya maarifa
Detailed knowledge of:
Method used: The students should be able to identify tools to be used and state procedures of constructing half turn stair
Principles: The student should be able to explain principles related to half turn stair
Theories: The students should be able to explain important aspects to consider when constructing half turn stair
Circumstantial knowledge: Workshop safety
Swali
What is the tread in a stair?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado