Column formwork is a temporary mould or frame used in construction to shape wet concrete into columns of the desired size and shape until the concrete hardens. It is made from materials such as timber, plywood, steel, aluminium, or plastic. Column formwork is essential in reinforced concrete construction because it provides structural support and ensures the column achieves its designed strength and dimensions.
Understanding each component helps you assemble the formwork correctly.
Panels
Panels are the main structural components that form the shape of the column. They are typically made from plywood, timber, plastic, or steel. Panels can be square, rectangular, or circular depending on the column design. They are versatile and reusable, making them cost-effective for multiple construction projects.
Ties and Wedges
Ties are tensile units that connect opposite sides of the formwork to resist the pressure of fresh concrete. They maintain the correct column width and prevent the panels from bulging outward. Wedges are used to connect column boxes and keep the formwork tightly in place during concrete pouring.
Anchors
Anchors are devices embedded in the concrete during placement to secure the formwork. External fasteners work together with anchors to hold the formwork steady. Anchors are removed after the concrete has set and the formwork is stripped away.
Clamps or Yokes
Clamps or yokes are hardware pieces used to keep the panels in position. They wrap around the formwork assembly and hold the sides together firmly. Yokes are particularly useful for maintaining alignment and preventing the formwork from shifting during construction.
Props or Double-Headed Jacks
Props and double-headed jacks provide adjustable load-bearing support. They are used when column formwork components need to be removed while still providing support to the floor or ceiling above. These components allow for precise height adjustment and easy stripping of the formwork after concrete hardens.
Follow these steps in order to construct a proper column formwork.
Step 1: Identify Materials and Tools
Gather all required materials and tools before starting:
Materials: Timber or marine boards, releasing agent, wire nails or screws, form ties and spacers, lumber or metal studs, shims or wedges.
Tools: Tape measure, pencil, hand saw, claw hammer, spirit level, try square, building square, ladder, chisels, carpenter's pencil, F-clamp, plumb bob, and safety gear.
Step 2: Plan and Design
Study the architectural and structural drawings to understand the column dimensions and reinforcement details. Determine the type of formwork needed based on column size and project requirements. For round columns, plan to use circular formwork systems or segmental panels.
Step 3: Prepare Materials and Tools
Ensure all formwork panels and support materials are in good condition and free from defects. Check that panels are not cracked or warped. Organize all tools within easy reach at the construction site.
Step 4: Set Out the Formwork
Clear the area around the column location. Ensure the base where the formwork will be placed is level and stable. Construct the formwork panels according to the column dimensions shown in the drawings. Place the assembled formwork around the column reinforcement (rebar). Verify that the formwork is aligned properly with the column layout.
Step 5: Secure the Formwork
Install form ties to hold the panels together and maintain the correct column width. Space the ties at regular intervals as specified in the design. Ensure all form ties are securely fastened. Insert spacers between the formwork and the reinforcement to maintain proper concrete cover over the rebar.
Step 6: Brace the Formwork
Ensure the steel reinforcement is correctly positioned inside the formwork and properly tied. Install additional bracing or supports to prevent deformation during concrete pouring. Check that the formwork can withstand the pressure of wet concrete without bulging or shifting.
Step 7: Apply Releasing Agent
Apply a releasing agent to the inner surfaces of the formwork before pouring concrete. This prevents concrete from sticking to the formwork and facilitates easier removal after the concrete sets.
Step 8: Check Level and Plumb
Use a spirit level and plumb bob to verify that the formwork is perfectly vertical and aligned. Make any necessary adjustments before proceeding to concrete pouring.
A construction site in Dar es Salaam requires a square column formwork with dimensions 300 mm × 300 mm and a height of 3,000 mm. The formwork will be constructed using plywood panels.
Solution:
-
Calculate panel dimensions: Cut four panels each measuring 300 mm × 3,000 mm.
-
Prepare the base: Ensure the concrete foundation is level and clean.
-
Assemble panels: Join the four panels using cleats at the corners. Use a try square to ensure all corners are at 90 degrees.
-
Install ties: Place form ties at intervals of approximately 600 mm vertically, starting from the base.
-
Add braces: Install diagonal braces on two opposite sides to prevent bulging.
-
Check verticality: Use a spirit level to confirm the formwork is plumb. Adjust using wedges if necessary.
-
Apply releasing agent: Coat the inner surfaces with releasing agent before concrete pouring.
This procedure produces a stable formwork ready to receive concrete.
Always wear appropriate Personal Protective Equipment (PPE) including safety boots, helmet, gloves, safety goggles, and overalls. Follow proper lifting and handling techniques when moving heavy panels and props. Ensure all formworks and supports are securely installed before pouring concrete. Check the stability of the formwork regularly and make necessary adjustments to prevent accidents.
- Column formwork is a temporary mould that shapes concrete columns until they harden.
- Main parts include panels, ties, wedges, anchors, clamps or yokes, and props.
- Follow the correct sequence: plan, prepare, set out, secure, brace, and check.
- Always apply releasing agent before concrete pouring.
- Safety gear must be worn at all times during construction.
In Tanzania, column formwork is commonly used when constructing multi-story buildings in cities like Arusha, Mwanza, and Dodoma. For example, a small-scale contractor building a two-story shop in Morogoro would need to construct column formwork to create the reinforced concrete columns that support the floors. Understanding column formwork enables a builder to safely create strong structural columns for houses, shops, and other buildings using locally available timber and plywood materials.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Draw a column formwork
- Interpret the drawings
- Calculate materials required
- Erect props for form work
- Fix form work
- Level and reinforce form work
- Dismantle the form work
- Clean tools and work place
- Store tools to a safe place
Tathmini ya matokeo
Column formworks constructed as per the drawings and technical specifications
Tathmini ya maarifa
Detailed knowledge of:
Method used: The student should be able to explain methods related to constructing column formwork
Principles: The student should explain principles for constructing column formworks
Theories: The students should explain theories related to constructing column formworks
Circumstantial knowledge: The students should explain detailed knowledge related to constructing column formwork
Swali
What is the primary purpose of column formwork in construction?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado