Constructing Upper Floor Shuttering
Upper floor shuttering is a temporary mould form used to hold wet concrete in place until it sets and hardens, creating a floor slab. Setting up forms for the floor is a critical step in concrete construction because floors require a large area of formwork to receive fresh concrete. The upper floor form consists of timber boards or plywood sheets supported on a framework and resting on a series of timber joists, which are vertically supported by timber or metal props.
Failure of the formwork to support the floor results from improper or inadequate shoring. The shores that support slab-forming systems must have sufficient load-carrying capacity, and they must be securely fastened at the bottom and top ends to prevent movement or displacement while in use.
The shuttering system for upper floors consists of two main parts: the beam-forming system and the slab-forming system. Each part includes specific components that work together to support the wet concrete until it hardens.
Slab-Forming System
The components of a slab-forming system for beam and slab concrete structures are made of timber or steel. It consists of:
Decking — This is the solid plywood panels that form the floor of the formwork against which fresh concrete is placed. Sheets of ply-form or plywood are commonly used. It provides resistance to the vertical pressure of the freshly placed concrete.
Joists — These are members under the decking that provide support for the floor decking. Joists are single members of wood material, thick with a depth that depends on the loads applied to the form and span length of the joist. The maximum spacing of joists is determined by the allowable span length of the decking that rests on the joists.
Stringers — These are members under the joists that provide support for the joists. Stringers are single members of wood material, thick with a depth that depends on the loads applied from the joists and the span length of the stringer.
Shores — These are members that support the joists and stringers, and beam bottoms for beam-slab forming systems. Shores may be single wood posts, single steel joists, or shoring frames.
Beam-Forming System
This is the part of the shuttering that moulds the beam shape. The form for concrete beams consists of the beam soffit (bottom) and the supporting planks.
Beam soffit (bottom) — Can be made from one or more dressed planks with the required width. If more than one plank is used, they should be cleated together on the underside at intervals of about 1 metre. The beam bottom may also be plywood, backed by dimension lumber laid in a flat position or in vertical direction to provide more resistance to bending and deflection.
Side forms — Made of plywood panels or boards, held together with 50 mm × 100 mm cleats. Side forms may also be made with boards, held together with 2" × 4" cleats. They are held together with form ties.
Ledgers — Attached to the vertical blocking, they carry the weight from the joist to the shore.
Kickers — At the bottom of the side form, they resist the lateral pressure from the concrete.
The spacing of shores under beam bottoms is limited by the strength of the beam bottom in bending, shear, and deflection, as well as by the capacities of the shores.
Note: 2" and 4" refer to 50 mm and 100 mm, respectively.
The following is a step-by-step procedure for constructing upper floor shuttering:
-
Review structural drawings — Confirm slab thickness, beam dimensions, and all relevant measurements.
-
Erect supports — Mark prop locations as per design in respective grid. Install vertical props secured well to soleplate and wedges. Ensure soleplates are on firm ground or floor. Fix the beam's tree head, align it vertically, and brace it using struts to ensure its stability and rigidity.
-
Check alignment — Use a spirit level to ensure each prop is perfectly plumb. Verify the height against the reference level and make sure the head is horizontal to create a stable, wobble-free support.
-
Lay plywood sheets — Place horizontal plywood sheets over the tree head. Erect the vertical side of the beam (plywood) and support it with kicker, blocking, and strut to the tree head.
-
Install slab decking — Lay plywood sheets over secondary beams to form decking. Secure them with nails to prevent movement and seal gaps with tape to avoid slurry leakage. Install vertical shutters at slab edges supported by kickers. Check the beam deck flatness using a straight edge.
-
Final inspection — Check level and alignment using a dumpy or laser level, ensuring no gaps greater than 2 mm at joints. Verify beam dimensions from drawings and check for deflection.
-
Clean and store — Clean the working place, tools, and store tools in a proper place for future use.
Given:
- Slab dimensions: 2.5 m × 3 m × 0.25 m
- Four beams of 250 mm × 400 mm
- Four columns of 250 mm × 250 mm
- Tank elevated 4 m high from ground floor
Procedure:
-
Review the structural drawings — Confirm that the slab thickness is 250 mm, beam dimensions are 250 mm × 400 mm, and the tank is elevated 4 m.
-
Erect supports — Mark prop locations in a grid pattern. Install vertical props at specified intervals, ensuring they are secured to soleplates on firm ground. Fix tree heads for beam support and brace with struts.
-
Check alignment — Use a spirit level to ensure all props are plumb. Verify heights against the reference level (4 m from ground).
-
Construct beam shuttering — Lay plywood sheets over tree heads. Erect vertical side plywood for beams, supporting with kickers and struts.
-
Construct slab decking — Place plywood sheathing over secondary beams, ensuring tight joints. Seal gaps with tape to prevent concrete leakage. Install vertical edge formwork with a slope of 1–2% for water drainage.
-
Final checks — Use a laser level to check level and alignment. Ensure all joint gaps are less than 2 mm. Verify all beam dimensions match the drawings.
-
Clean up — Remove debris and store all tools properly.
When constructing upper floor shuttering, the following safety measures must be observed:
- Wear safety helmet, safety boots, gloves, and safety goggles at all times
- Use ladders or scaffolding properly when working at height
- Ensure props are firmly secured on the ground or floor to prevent sinking
- Check all joints and seals for gaps to prevent concrete leakage
- Provide proper bracing to avoid formwork collapse during concreting
- Inspect formwork for stability before allowing workers on the formwork
In Tanzania, a form three student learning this topic might apply these skills when assisting a local builder or mason in their community. For example, when constructing a two-story house in a village like Mbeya or Arusha, the student could help erect temporary formwork for an upper floor slab, ensuring it is properly supported with props and that the concrete does not leak through gaps — a common problem when inexperienced builders attempt concrete work without proper shuttering knowledge.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Draw balcony shuttering
- Interpret the drawings
- Calculate materials required
- Erect props for shuttering
- Fix shuttering
- Level and reinforce form work
- Dismantle the shuttering
- Clean tools and work place
- Store tools to a safe place
Tathmini ya matokeo
Constructed upper floor shuttering conforms to drawing and technical specifications
Tathmini ya maarifa
Detailed knowledge of:
Method used: The student should explain methods related to constructing upper floor shuttering
Principles: The student should explain principles related to constructing upper floor shuttering
Theories: The students should explain theories related to constructing upper floor shuttering
Circumstantial knowledge: The students should explain detailed knowledge related to constructing upper floor shuttering
Swali
What is the primary function of shores in upper floor shuttering?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado