Mada za sehemu hiiConstructing centeringMada 3
- Constructing semi-circular centre
- Constructing segmental centre
- Constructing elliptical centre
Constructing a Segmental Centre
A segmental centre is the temporary formwork (shuttering) used to support brickwork or masonry during the construction of a segmental arch — an arch whose curve is part of a circle but with a rise smaller than a semicircle. Unlike a semi-circular arch where the rise equals half the span, a segmental arch is flatter, allowing for larger spans without requiring excessive height. This makes it ideal for bridges and wider openings in buildings.
The centre must remain in place until the mortar has gained sufficient strength to hold the arch shape on its own.
Before constructing the centre, you must calculate the radius of the arch using the span and rise.
- Span (S): The horizontal distance between the two supports (jambs) of the arch.
- Rise (h): The vertical distance from the springing line (base of the arch) to the highest point of the intrados (inner curve).
Formula for Radius
R=8hS2+4h2
Where:
- R = radius of the segmental arch
- S = span of the arch
- h = rise of the arch
A segmental arch has the following dimensions:
- Span (S) = 1.2 metres
- Rise (h) = 0.3 metres
- Arch thickness = 100 mm
- Width of centre = 200 mm
Calculate the radius (R):
R=8hS2+4h2=8×0.31.22+4(0.3)2=2.41.44+0.36=2.41.80=0.75 m
The radius is 0.75 metres (75 cm).
Step 1: Design the Arch Centre
Understand the geometry. A segmental arch is part of a circle. You will create a curved template (rib) that matches the intrados of the arch.
Step 2: Mark and Cut the Arch Ribs
- On a plywood sheet (18–25 mm thick), draw a baseline equal to the span (1.2 m).
- Using a trammel or compass set to the calculated radius (0.75 m), draw the arc (the curve of the arch).
- Cut two identical arch ribs using a jigsaw or handsaw.
- Number of ribs: Use at least 2 ribs; more ribs may be needed for longer spans.
Step 3: Cut and Assemble Supports
- Cut softwood battens to create vertical struts (supports) and a base ledger (horizontal beam at the bottom).
- Position the struts at regular intervals, typically every 200–300 mm along the length of the ribs.
- Nail or screw the arch ribs securely to the struts.
- Attach a bottom base plate (ledger) to connect the struts and provide stability.
Step 4: Test and Fit the Centre
- Place the finished centre between two temporary supports (such as bricks or concrete blocks) positioned at the arch opening.
- Check that the centre sits level and fits snugly within the span.
- Ensure the curve is smooth and matches the designed arch shape.
Step 5: Final Checks
- Sand any rough edges to prevent injury and ensure smooth handling.
- Label key parts: ribs, struts, base, and braces.
- Inspect all joints to ensure they are tight and secure.
- Plywood sheet (18–25 mm thick) or softwood planks for ribs
- Softwood battens for struts and ledgers
- Nails or screws
- Wood glue (optional, for added strength)
- Tape measure
- Pencil
- Compass or trammel (for drawing arcs)
- Handsaw or jigsaw (for cutting curves)
- Hammer or screwdriver
- Square
- Sandpaper
- Wear safety boots and gloves when handling timber and tools.
- Use a helmet when working in areas where objects may fall.
- Ensure the working area is clear of debris.
- Secure all joints properly to prevent collapse during brickwork or masonry placement.
- Do not remove the centre until the mortar has fully set — premature removal can cause the arch to collapse.
| Feature | Segmental Centre | Semi-circular Centre |
|---|---|---|
| Shape | Part of a circle (rise < half span) | Full half-circle (rise = half span) |
| Span capability | Can span larger widths | Limited by height |
| Rise | Smaller rise | Higher rise |
| Common use | Bridges, wider openings | Door and window arches |
- Ribs deflect inward under weight: Ensure struts are properly braced and joints are tightly secured. Add diagonal bracing if needed.
- Curve is not smooth: Use a trammel or compass to draw the arc accurately. Check the radius calculation.
- Centre wobbles: Verify that the base is level and struts are vertical. Add bottom cross-braces for stability.
In Tanzania, a segmental centre is commonly used when constructing bridge culverts along rural roads or when building arched doorways and windows in traditional Swahili-style buildings found in Stone Town, Zanzibar, and other historic settlements. A artisan builder in Mwanza or Dodoma would calculate the radius using the span and rise, then construct the timber centre to support the arch bricks until the mortar sets — ensuring a durable, load-bearing arch that can support the structure above.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Interpret drawings
- Calculate materials required
- Prepare ribs
- Prepare laggings
- Fix lagging to ribs
- Erect and reinforce centering
- Dismantling centering
- Clean work place and tools
- Store tools to safe place
Tathmini ya matokeo
Constructed segmental centering conform technical specifications
Tathmini ya maarifa
Detailed knowledge of:
Method used: The student should explain methods related to construct segmental centre
Principles: The student should explain principles related to construct segmental centre
Theories: The students should explain theories related to construct segmental centre
Circumstantial knowledge: Safety rules
Swali
What is the primary function of a segmental centre in construction?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado