Mada za sehemu hiiErecting shoringMada 3
- Erecting racking shoring
- Erecting flying shoring
- Erecting dead shoring
Erecting Dead Shoring
Dead shore is a shoring system used to temporarily support a structure when the bottom part of a wall has been removed to create an opening or to rebuild a deficient load-bearing wall. It can also be used for increasing the depth of an existing foundation during underpinning work.
Dead shoring transfers the load from the structure above through horizontal beams (needles) to vertical posts (dead shores), then to the ground through sole plates. This allows workers to safely create openings in walls or repair foundations without risking collapse.
The dead shore system consists of several key components that work together to support the structure:
Needles are thick wooden beams or steel sections inserted into holes made in the wall. They collect the load from the structure above and transfer it to the dead shores. Needles are typically spaced at 1–2 metre intervals, with a minimum of three needles used for any opening.
Dead shores are vertical posts that support the needles at their ends. They carry the load from the needles and transfer it to the sole plates below. These are usually made from timber posts (approximately 150mm × 150mm) or adjustable steel props.
Sole plates (also called sleepers) are horizontal timber or steel plates placed on the ground to distribute the load from the dead shores over a larger area. This prevents the props from sinking into the soft ground.
Folding wedges are wooden inclined planes placed between the sole plate and the dead shore. They allow for fine adjustment of the shoring system to ensure tight fitting and proper load transfer.
Head plates are horizontal beams placed at the top of the dead shores to evenly transfer the load from the structure above to the vertical props.
Braces and struts are diagonal members that provide lateral stability to prevent the shoring from swaying or collapsing sideways.
When constructing dead shoring, the following points must be considered:
-
Spacing: Dead shores should be placed at approximately 2000mm centre-to-centre and positioned under the piers between windows. Any windows near the shores should be strutted to prevent distortion of the openings.
-
Needle spacing: Needles are typically spaced at 1–2 metre intervals. A minimum of three needles should be used for an opening to ensure adequate load distribution.
-
Load capacity: The section of needles and dead shores must be adequate to transfer the load from the structure above. The size depends on the weight being supported.
-
Bracing: All components must be suitably braced for external wall openings. Note that the length of outer dead shores will be greater than the inner ones.
-
Ground conditions: Sole plates must be placed on firm, level ground to prevent sinking. The ground should be compacted before placing sole plates.
-
Removal timing: Shores should be removed only when the new work has gained sufficient strength, but in no case less than 7 days after the completion of the new work.
Step 1: Assess the Structure
Identify the load-bearing walls or beams that need support. Check for cracks, weak points, and determine how the load is distributed throughout the structure. This assessment determines where needles will be inserted and where dead shores will be positioned.
Step 2: Plan the Shoring Layout
Determine prop spacing, typically 1–1.5 metre intervals. Calculate the required load capacity based on the weight of the building above. Mark the positions where holes will be made for needles and where props will stand.
Step 3: Install Sole Plates
Place sole plates on firm, level ground to prevent sinking. Use timber or steel plates to distribute the weight evenly. The sole plates should be large enough to prevent the props from pressing into the soil.
Step 4: Erect Vertical Props
Position adjustable steel props or timber posts vertically (plumb). Use a spirit level to ensure they are perfectly vertical. Temporarily brace the props to prevent swaying during installation.
Step 5: Install Head Plates and Needles
Place horizontal beams (needles) through holes made in the wall at the top of the dead shores. These needles transfer the load from the structure above to the vertical props. Ensure even contact with the structure above.
Step 6: Tighten and Secure
Use wedges or screw jacks to apply slight upward pressure and ensure tight fitting. Add diagonal braces between props for lateral stability. All connections should be securely fastened with nails, bolts, or clamps.
Step 7: Final Inspection
Check that all props are rigid, level, and bearing load evenly. Verify that there is no visible sagging or movement. Monitor the shoring regularly for any settling or movement over time.
Problem: A wall is to have a doorway opening 2.4 metres wide. The wall is 3 metres high and has windows between the existing door and the corner. Determine the basic arrangement of dead shores.
Solution:
-
Needle spacing: With a 2.4m opening, needles should be placed at approximately 1.2m intervals. This requires 3 needles minimum (one at each end of the opening and one in the middle).
-
Prop positioning: Dead shores should be placed at approximately 2m centre-to-centre. Since windows are present, shores should be positioned under the piers between windows, with windows strutted to prevent distortion.
-
Typical arrangement:
- Needle 1: 0.6m from left corner
- Needle 2: 1.2m from Needle 1 (centre of opening)
- Needle 3: 0.6m from right corner
- Dead shores placed at each needle location, both inside and outside the wall
-
Wall openings for needles: Holes are made in the wall at a suitable height, typically 1.2 to 1.8 metres above floor level.
When erecting dead shoring, always observe the following safety measures:
- Wear appropriate PPE including a helmet, safety boots, overalls, and leather gloves
- Ensure the ground is firm and level before placing sole plates
- Check all props are vertical using a spirit level
- Ensure all braces and wedges are tightly fitted
- Never work under an unsupported structure
- Inspect the shoring regularly for movement or settling
- Only remove shores after new work has gained sufficient strength (minimum 7 days)
In Tanzania, dead shoring is commonly used when homeowners in areas like Mwanza or Dodoma want to modify their traditional houses by creating larger doorways or windows for better ventilation and light. For example, a shop owner in Arusha may need to create a wider entrance to accommodate more customers, requiring dead shores to temporarily support the wall while the opening is being made. The skills learned in erecting dead shores enable carpentry graduates to offer specialised temporary support services during building renovations, creating income-generating opportunities in local construction projects.
Jinsi utakavyotathminiwaTathmini ya mchakato · Tathmini ya matokeo · Tathmini ya maarifa
Tathmini ya mchakato
The student should be able to:
- Prepare shoring members
- Calculate materials required
- Set /prepare shoring
- Erect shoring
- Reinforce shores
- Dismantle shores
- Clean work area and tools
- Store tools at a safe place
Tathmini ya matokeo
Constructed dead shores conform to technical specifications
Tathmini ya maarifa
Detailed knowledge of:
Method used: The student should explain methods related to erecting dead shoring
Principles: The student should explain principles related to erecting dead shoring
Theories: The students should explain theories related to erecting dead shoring
Circumstantial knowledge: The students should explain detailed knowledge related to erecting dead shoring
Swali
What is the primary function of needles in a dead shore system?
Ingia ili kuwasilisha jibu lako na lihesabiwe katika umahiri wako.
Ingia ili kufanya mazoeziMwalimu
Umekwama? Niulize chochote kuhusu mada hii.
Ingia ili kumuuliza Mwalimu wa AI wa Sonza kuhusu swali hili.
Ingia ili kuulizaMajadiliano
Hakuna maswali bado